2019 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
2019 Pavement Preservation Program - Chip, Fog and Slurry Seals (M19500) | TBD | 32.53 |
2019 Pavement Preservation Program - Full Depth Reclamation and Overlays (C19600) |
TBD | 14.82 |
2019 Totals:
|
|
47.35 |
2018 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
2018 Pavement Preservation Program - Chip Seals & Overlays | TBD | 13.11 |
2018 Pavement Preservation Program - Full Depth Reclamation & Overlays (C18004) |
TBD | 7.56 |
East Watmaugh Road Overlay |
TBD | 2.3 |
Peru Road Overlay | TBD | 0.51 |
2018 Storm Damage- Full Depth Reclamation and Overlays (M18059) | TBD | 22.31 |
2018 Totals:
|
|
45.80 |
2017 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
2017 Pavement Preservation Program - Overlays, FDR & CIR (C17002) |
TBD | 7.99 |
2017 Pavement Preservation Program - Chip, Fog & Slurry Seals (M17018) |
TBD | 40.83 |
2017 Pavement Preservation Program - Rehabilitation of Various Streets (C14040) |
TBD | 5.59 |
Mueller Road Overlay | TBD | 0.43 |
2017 Totals:
|
54.84 |
2016 Projects
|
Construction Cost | Miles Treated |
---|---|---|
2016 Maintenance Chip Seals |
TBD
|
32.79
|
2016 Pavement Preservation Program, Bonded Wearing Course & Overlay |
TBD
|
19.59
|
2016 Pavement Preservation Program, Full Depth Reclamation & Chip Seal |
TBD
|
21.59
|
2016 Totals:
|
|
73.97
|
2015 Projects
|
Construction Cost | Miles Treated |
---|---|---|
2015 Maintenance Chip Seals |
1,036,788
|
21.49
|
2015 Totals:
|
1,036,788
|
21.49
|
2014 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
2014 Pavement Preservation Program, Bonded Wearing Course (M01428) |
4,485,743
|
16.69
|
2014 Pavement Preservation Program, Full Depth Reclamation (C014020) |
4,774,169
|
10.06
|
2014 Maintenance Chip Seals |
643,369
|
16.97
|
2014 Totals:
|
9,903,281
|
43.72
|
2013 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
2010 Pavement Preservation Program (M10001) |
4,895,210
|
21.64
|
2012 Asphalt Overlay Program (C11008) |
5,220,043
|
8.19
|
2013 Pavement Preservation Program Bonded Wearing Course (M12004) |
1,373,977
|
7.88
|
2013 Pavement Preservation Program Overlays (C12018) |
6,168,538
|
12.27
|
Airport Blvd Signal at Fulton Road (C05016) |
* 1,477,192
|
1.01
|
2013 Maintenance Chip Seals |
709,423
|
14.70
|
2013 Totals:
|
19,134,960
|
65.69
|
2012 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
Arnold Drive Shoulder Improvements and Overlay (C01330) |
* 764,489
|
0.94
|
Western Avenue Bike Shoulder Widening, Phase II (C03408) |
* 793,232
|
0.27
|
2012 Totals:
|
1,557,721
|
1.21
|
2011 Projects
|
Construction Cost
|
Miles Treated
|
---|---|---|
2010 ARRA Cost Savings Overlay Project (C10001) |
2,385,973
|
6.31
|
2011 Climate Initiative Cold-In-Place Recycling Project (C10008) |
1,316,845
|
2.29
|
Western Avenue Bike Shoulder Widening, Phase I (C03020) |
* 943,781
|
0.30
|
2011 Totals:
|
9,934,246
|
8.90
|