Skip to Content

Road Maintenance Update

Published: June 01, 2016

This week, the bridge crew will be installing guardrails in the Summerhome Park Road viaduct area, where paving work was completed last Thursday. One lane traffic controls will be set up daily from 7:30 am to 4 pm with only minor delays. Additionally, bridge crew staff will be installing bridge plates with a crane at both the Asti and Odd Fellows summer crossings this week. 

Road work in preparation of summer chip seals are scheduled this week along Burnside Road and Chalk Hill Road. The Culvert crew will be replacing failed cross culverts along Burnside Road between Watertrough Road and Barnett Valley Road. Road crews will be doing asphalt repairs along Burnside Road within the same areas. One lane traffic controls will be in place for both projects with minor delays. 

Short delays can be expected along Chalk Hill Road, as road crews will be doing asphalt repairs between Pleasant Avenue to Morse Road.