Hood Mountain Lawson Expansion - Project Detail

New Trail Construction

The construction of the 1.5-mile Lawson Trail began October 4, 2019. The trail is open for public use.

Project Timeline

Timeframe Project Process 
June 11, 2018Board of Supervisors approve the Master Plan and Final IS/MND, and Final Notice of Determination 
Summer/Fall 2018Project Design and Engineering, and Trail Log Development 
Spring 2019 Construction Bid 
Fall 2019/Spring 2020 Construction Implementation 
Summer 2020 New trails and other feature open to the public 
September 2020Park and trail damaged from the Glass Fire and both are closed
June 1, 2021Sections of the Lower Johnson Trail and full length of Lawson Trail open for public use

Public Meetings

Public Hearings and Community Workshops were held on the master planning process on: 

  • November 8, 2015 (Community Workshop #1)
  • May 19, 2016 (Community Workshop #2)
  • June 11, 2018 (Board of Supervisors adoption of Master Plan and certification of Initial Study/Mitigated Negative Declaration)

Please see calendar (past events) for details

Contact Information

Karen Davis-Brown, Planner II

Planning Division

Regional Parks
County of Sonoma
Business Hours
Monday – Thursday
7:00 AM – 4:30 PM
Contact us by Phone

Sign up for Planning Updates

Office Location

Sonoma County Regional Parks
2300 County Center Drive
Suite 120A
Santa Rosa, CA 95403

Google Maps™ Directions