Planned road maintenance projects this week will include roadside mowing along Annapolis Road, Stewarts Point Skaggs Springs Road, and in the rural Petaluma area. Roadside brushing is planned for road crews along Corona Road and Chalk Hill Road, and Cal Fire crews will be cutting roadside brush and vegetation on Chalk Hill Road on Tuesday and Wednesday, and Wednesday only on Warrington Road. 

Grinding and pavement repairs will be done on Burbank Drive in the Sonoma area Tuesday through Thursday. Road crews will be pothole patching as needed in other areas of the county.

The Bridge crew will continue work on Starrett Hill Road replacing a bridge viaduct. Starrett Hill Road remains closed during construction that is scheduled through April 20 th

The Culvert crew will be replacing a failed culvert on Cleveland Lane south of Bodega Avenue this week, one lane traffic controls with minor delays can be expected Monday through Thursday from 7:00 AM to 4:00 PM daily.

Lastly, the Traffic crew will be performing NPDES storm drain inspections and stenciling stop and stop bars at intersection in the Sonoma area.

Contact Information

Business Hours
Monday – Friday
8:00 AM – 5:00 PM
Contact us by Phone
Office Location
La Plaza B
2300 County Center Drive
Suite B 100
Santa Rosa, CA 95403
38.462023, -122.725381

County Roads

Report a Road-Related Issue

Construction sign thumb

Report potholes, fallen trees, flooding, and other road-related issues.