Project Timeline

Timeframe  Project Process 
June 11, 2018 Board of Supervisors approve the Master Plan and Final IS/MND, and Final Notice of Determination 
Summer/Fall 2018 Project Design and Engineering, and Trail Log Development 
Spring 2019  Construction Bid 
Fall 2019/Spring 2020  Construction Implementation 
Summer 2020  New trails and other feature open to the public 
September 2020 Park and trail damaged from the Glass Fire and both are closed
June 1, 2021 Sections of the Lower Johnson Trail and full length of Lawson Trail open for public use

Public Meetings

Public Hearings and Community Workshops were held on the master planning process on: 

  • November 8, 2015 (Community Workshop #1)
  • May 19, 2016 (Community Workshop #2)
  • June 11, 2018 (Board of Supervisors adoption of Master Plan and certification of Initial Study/Mitigated Negative Declaration)

Please see calendar (past events) for details